TM 9-6115-661-13&P
This task covers: a. Removal
c. Installation
b. Repair
INITIAL SETUP
Tools
Equipment Conditions
Tool Kit, General Mechanic's
Reference
(item 1, appendix B)
Both generator sets shut down,
Materials/Parts
paragraph 2-5.3.1.
Trailer support devices are
Terminal, Load
lowered, paragraph 2-3.2.1.
Wire, Round Steel, 0.072 inch diameter
QQ-W-423 Composition 302
REMOVAL
1. Remove 21 screws (2, figure 4-15), lock washers (3), and flat washers (4).
2. Release clamping catch (5) and open load terminal door (1).
CAUTION
The control panel connector P3 is connected to connector J4. Movement of
the switch box cover is limited. To prevent damage to control panel wiring
harness, use caution removing switch box cover. Failure to observe this
caution can result in equipment damage.
3. Carefully position switch box cover (15) in front of switch box assembly.
4. Disconnect P3 (6) from J4 (7).
5. Remove switch box cover (15).
6. Disconnect external load terminal lead from the defective terminal (14).
NOTE
For removal of ground load terminal go to step 8.
7. Remove nut (8), internal tooth lock washer (9), and leads (10) from defective load terminal (14).
8. Remove nut (11) that secures the load terminal (14) to the mounting plate.
9. Remove load terminal (14).
|