TM 9-6115-661-13&P
14. Connect P3 (7) to J4 (8).
15. Position switch box cover (19) over switch box assembly and align mounting holes.
16. Install a flat washer (1), new lock washer (2) and screw (3) that secure the switch box cover (19).
INSTALLATION
1. Position switch box assembly on switch box support (21) and front platform.
2. Route electrical leads (20) and cable harness (7) through the power cable sock (12).
3. Align mounting holes of the switch box assembly and switch box support (21).
4. Install four screws (6), eight flat washers (5) and nuts (14), to secure switch box assembly.
5. Connect P1 (8) to J16 (7) of generator set.
6. Connect W1, W2, W3, W4 and W5 to the load terminals (9) of the generator set as follows:
a.
Connect
W1
to L1.
b.
Connect
W2
to L2.
c.
Connect
W3
to L3.
d.
Connect
W4
to LO.
7. Connect W5 to GND (10).
This task covers: a. Removal
c. Installation
b. Repair
INITIAL SETUP
Tools
Equipment Conditions
Tool Kit, General Mechanic's
Reference
(item 1, appendix B)
Both generator sets shut down,
Materials/Parts
Trailer support devices are
lowered, paragraph 2-3.2.1.
Washer, Lock
|