TM 9-6115-661-13&P
(5) Refer to TM 9-2330-202-14&P (1 ton trailer) or TM 9-2330-392-14&P (high mobility trailer) and
disconnect trailer from towing vehicle.
(6) Pull out pin (1, figure 2-5) that secures rear leveling-support jack (2) in travel position,
(7) Pull rear leveling-support jack (2) down. Insert pin (1) in bracket (3) to secure rear leveling-
support jack (2) in down position.
(8) Turn leg base (4) until it makes firm contact with ground.
d. Remove fire extinguisher from bracket. Locate fire extinguisher on ground away from equipment.
Field Manual 20-31. Typical ground rod installations are shown in Figure 2-6. If a ground rod is used,
install and connect it as follows:
NOTE
The Power Plant AN/MJQ-39 consists of two power units. One ground rod
must be installed for each power unit.
|