TM 9-2320-209-20-3-1
TRANSMISSION TRANSFER SYSTEM GROUP MAINTENANCE
Section I. SCOPE
cedures for the transmission transfer control and linkage assembly for which there
are authorized corrective maintenance tasks at the organizational maintenance level.
maintenance is authorized at the organizational maintenance level are covered in this
chapter.
Section II.
TRANSMISSION
TRANSFER
CONTROL
AND
LINKAGE
ASSEMBLY
REMOVAL AND REPLACEMENT (TRUCKS M49A1C, M49A2C, M50A1, M50A2,
M50A3, M756A2, and M764).
NOTE
Procedures given are the same for both air actu-
ated positive lockup transmission transfer with
power takeoff, and non air actuated positive
lockup transmission transfer with power takeoff,
except where noted.
Vise grip pliers
3/4-inch socket wrench
TOOLS:
Small hammer
3/4-inch open end wrench
13/16-inch open end wrench
18-inch ruler
5/8-inch wrench
Needle nose pliers
Drift punch
SUPPLIES:
None
PERSONNEL:
TW O
Truck parked, engine off, handbrake set.
EQUIPMENT
CONDITION:
Preliminary Procedure. Remove intermediate and rear tunnels. Refer to
a.
Part 3, para 18-5.
b. Removal of Transmission Shift Lever and Linkage (Trucks M756A2 and M764).
Refer to para 9-4.
|