TM 10-5411-233-13&P
CARGO BED COVER (CBC), TYPE III, 2 1/2 T CARGO TRUCK, LMTV, AND LMTV TRAILER 0014 00
UNIT MAINTENANCE
INSTALLATION OF MOUNTING KIT FOR M1078, 2 1/2 TON LMTV
THIS SECTION COVERS:
Installation
INITIAL SETUP
Truck bed clean and free of debris
CBC prepared as detailed in WP 0010 and positioned near the vehicle on pallet
Mounting Kit unpacked and hardware organized on work surface
Side Panels and Tailgate removed (TM 9-2330-394-13&P)
Maintenance Level
Materials/Parts
Unit
Tools and Special Tools
General Mechanic Tool Kit (WP 0041, Table 2, Item 1)
Lifting Device (1 Ton minimum)
Caulking Gun, Ratchet Drive (WP 0041, Table 2, Item 7)
General. Before the Cargo Bed Cover can be installed on the bed of the M1078, 2 1/2 T LMTV, the bed
surface should be cleaned of any foreign matter or other debris that would interfere with the installation
process.
INSTALLING WEATHER STRIPPING ON THE CBC
Once the CBC has been separated from its shipping pallet and prepared for installation as outlined in the
UNPACKING section of WP 0010, it must be extended to its operational position, if necessary, as
outlined in WP 0005 entitled EXTENDING THE CARGO BED COVER TO AN OPERATIONAL
POSITION.
Once the CBC (1) has been raised to an operational position, the CBC must be lifted and placed on
supporting blocks (2) in order to gain access to the lower edge of the CBC for the installation of the
weather stripping. A hoisting sling must be attached to lift the CBC in accordance with WP 0005. When
initially positioning the blocks, it is best to place them first at the fore and aft ends to allow access to the
left and right sides of the CBC and then to move them to the left and right sides to gain access to the fore
and aft ends.
Once the CBC has been safely blocked, the weather stripping can be installed. Two thicknesses of
weather stripping, individually labeled 3/16 inch and 1/8 inch, are included with the mounting plate
installation kit. They are both supplied in rolls of 50 feet.
Apply the 3/16 inch weather stripping (3) to the bottom edge (4) of the Cargo Bed Cover (1) by removing
the protective backing (5) from the weather stripping and pressing the adhesive side (6) into position. Do
NOT apply the weather stripping to the bottom of the carrier mounting angles (7). Be sure to allow the
weather stripping to extend beyond the corners of the CBC by approximately 2 inches.
Add an second layer of 1/8 inch thick weather stripping (8) over the initial layer of 3/16 thick weather
stripping (3). Be sure to stagger the joints when applying the second layer so that a weather stripping joint
on the first layer is not directly over a joint on the second layer. When complete, the total thickness of the
weather stripping on the underside of the CBC should be 5/16 inch (9).
In order to apply the weather stripping around the entire perimeter of the CBC, it will be necessary to lift
the CBC and reposition the blocks (2). Continue applying the 3/16 inch weather stripping (3) and 1/8 inch
0014 00-1
|