TM 9-6115-661-13&P
1. To shut down generator set, place AC CIRCUIT INTERRUPTER switch in the OPEN position.
m. On the switch box place ON LINE switch for the generator which is on line (3 or 6) to the OFF
position.
NOTE
At this time, allow generator set to operate five minutes with no load
applied.
n. On the generator set control panel rotate the MASTER SWITCH to the OFF position.
2-5.3.2 Operating Generator Sets in Parallel. The generator sets can be operated in parallel through
terminals, refer to paralleling procedures in TM 9-6115-643-10. When paralleling at the switch box,
perform the following procedures:
Prior to making any connections for parallel operation, ensure that there is
no input to the load and that the generator sets are shut down. Failure to
observe this warning can result in serious injury or death by electrocution.
WARNING
Never attempt to start the generator set if is not properly grounded.
Failure to observe this warning can result in serious injury or death by
electrocution.
Ensure that load requirement is equal to or below the combined rated capacity of the two generator
a.
sets.
b.
Perform the Preventive Maintenance Checks and Services (PMCS) listed as BEFORE in table 2-2.
Install load and paralleling cables.
c.
CAUTION
Do not close the AC CIRCUIT INTERRUPTER switch (13) on either of
the generator sets or close the load contactor at load until specifically
directed to do so. Closing any of these devices at any other time may
severely damage one or both of the generator sets.
Refer to paragraph 2-5.3.1 (step c through g) to a generator set and bring it on line.
d.
e.
On operating generator set (generator set 1) position UNIT-PARALLEL switch (16) to PARALLEL.
f.
Start generator set 2 and adjust voltage and frequency to match generator set 1.
At switch box, set generator set 2 ON-OFF switch (3 or 6) to ON (Switch box STATUS & ON-LINE
G.
lights for both generators should be lit).
2-40
|