TM 9-2330-391-10
LIGHT MATERIAL HANDLING CRANE (LMHC)
OPERATION
INITIAL SETUP
Maintenance Level
Personnel Required
Operator
Two
Tools and Special Tools
References
Wheel Chocks (Item 10, Table 2
GENERAL
This work package provides the data and procedures to be used by the Operator when
performing Light Material Handling Crane (LMHC) operations. Items covered include How
To Determine Required LMHC Settings, Reset The Circuit Breaker, Change LMHC Location,
Prepare LMHC For Use, Install Long Handle, Raise Boom, Telescope Boom, Swing Boom,
Raise And Lower Load, Install Short Handle, and Stow LMHC.
DETERMINE REQUIRED LIGHT MATERIAL HANDLING CRANE (LMHC) SETTINGS
1.
Determine the weight of load.
2.
Determine the radius from centerline of LMHC rotation to position of load.