TM 9-2320-361-24-2
FIELD MAINTENANCE INSTRUCTIONS
2-1/2 TON, 6X6, M44A2 SERIES TRUCKS (MULTIFUEL)
SIDE RAIL MAINTENANCE
REMOVAL, CLEANING, AND INSTALLATION
INITIAL SETUP:
Applicable Models
Materials/Parts (Contd)
M185A3, M109A3
Fifty-four plugs (item 310, WP 0470 00)
Tar (item 52, WP 0468 00)
Tools and Special Tools
Equipment Condition
General mechanic's tool kit
(item 116, WP 0469 00)
Parking brake set and wheels chocked
(TM 9-2320-361-10).
Materials/Parts
Battery ground cable disconnected
(WP 0126 00).
Fifty-four rivets (item 315, WP 0470 00)
NOTE
Side rails on both sides of van body are removed and installed
the same. This task covers one side.
REMOVAL
1. Drill fifty-four plugs (3) and rivets (2) out of side rail (4) and van wall (1).
2. Remove two side rails (4) from van wall (1).
CLEANING
Clean all tar out of rivet holes (5) and side rail (4).
INSTALLATION
NOTE
A sealer coat of hot tar must be applied to inside of rail in area
of rivet holes before installation.
1.
Install two side rails (4) on van wall (1) with fifty-four new rivets (2) and fifty-four plugs (3).
2.
Connect battery ground cable (WP 0126 00).
3.
Release parking brake and remove wheel chocks (TM 9-2320-361-10).