TM 9-2320-361-24-1
FIELD MAINTENANCE INSTRUCTIONS
2-1/2 TON, 6X6, M44A2 SERIES TRUCKS (MULTIFUEL)
TRANSMISSION REMOVAL
INITIAL SETUP:
Applicable Models
Equipment Condition
All
Parking brake set and wheels chocked
(TM 9-2320-361-10).
Tools and Special Tools
Battery ground cable disconnected
General mechanic's tool kit
Cab top removed
(item 1, WP 0469 00)
(if overhead lifting device is used)
Sling, engine and transmission
(TM 9-2320-361-10).
(item 91, WP 0469 00)
Transmission gearshift lever removed
Breaker bar, 1/2-in. drive
(item 6, WP 0469 00)
Cab tunnels removed (WP 0230 00).
Lifting device
Power takeoff propeller shaft removed
Two utility chains
(vehicles w/PTO installed) (WP 0346 00).
Transfer case to transmission propeller shaft
Personnel Required
removed (WP 0139 00).
Two
Intermediate propeller shaft removed
0131 00-1
|