Table 1-8. Organizational Preventive Maintenance Checks and Services Semiannual Schedule
for M756A2 Pipeline Construction Truck - Cont
Item
Procedures
Item
To Be
Check for and Have Repaired,
No.
Inspected
Replaced, Adjusted as Necessary
3
Body
1. Check that body subframe (1) is not cracked,
broken, and does not have broken welds. Check
that subframe is alined with truck chassis.
2. Check that mounting sills (2) and floorboards (3)
are not cracked, split, rotten, and do not have
loose or missing hardware.
3. Check that tailgate (4) and body panels (5) are
not bent, broken, and do not have broken welds.
4. Check that hardware for racks and troop seats
(6) is not loose or missing.
1-49
|