TM 9-2320-209-20-1
Table 1-8. Organizational Preventive Maintenance Checks and Services Semiannual Schedule
for M756A2 Pipeline Construction Truck - Cont
Item
Procedures
Item
To Be
Check for and Have Repaired,
No.
Inspected
Replaced, Adjusted as Necessary
2
(d) When drag brake is properly adjusted,
(cont)
unwind rest of cable (1). Refer to
TM 9-2320-209-10.
4. Check that cable (1) is not kinked, does not
have broken wires, or broken/loose clamps.
5. Check that drum (2) is not cracked, and does
not have broken welds.
6. Wind cable back on drum. Refer to
TM 9-2320-209-10.
7. Check adjustment of winch automatic brake.
Automatic brak e should hold a 1,000 pound
load without slipping. Refer to Vol 3,
chapter 19, para 19-3 for test and adjust-
ment procedures.
1-48
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |