TM 9-2320-386-24-1-2
0364 00
CRANKSHAFT AND BEARING SLEEVES MAINTENANCE (Contd)
7.
Check crankshaft (5) for end play by installing a dial indicator on cylinder block (7) with pointer on
end of crankshaft (5). Move crankshaft (5) to rear, zero dial indicator and then move crankshaft (5)
to front. The reading on the dial indicator represents end play.
8.
End play measurement must be 0.003-0.013 in. (0.07-0.32 mm). If not within limits, replace
bearings or crankshaft (5).
9.
Install timing gear housing (WP 0363 00).
10.
Install transmission adapter housing (WP 0307 00).
11.
Install pistons and connecting rods (WP 0361 00).
12.
Install camshaft (WP 0359 00).
13.
Install cylinder head (WP 0302 00).
14.
Install power plant (WP 0295 00).
2
LIFTING
DEVICE
3
1
4
LIFTING
STRAPS
4
4
5
6
6
6
7
~
8
END OF WORK PACKAGE
0364 00-5/6 blank
|